Subic power plant faces further delay
Posted 5 years ago
Photo Credit: elp.com
Redondo Peninsula Energy Inc. may put on hold the development of a 660-megawatt coal-fired power until 2020 due to construction issues, an official said over the weekend.
RP Energy is a joint venture among Meralco PowerGen Corp., Therma Power Inc. of the Aboitiz Group and Taiwan Cogeneration International Corp.
“The management of RP Energy have engaged a consultant and the consultant’s recommendation is to stabilize the slope first. Issues like this with geological conditions is very tricky. In fact, one of the recommendations I believe, is to let it rest for one rainy season and that’s rainy season up to 2020,” said Aboitiz Power chief operating officer Manny Rubio said.
“There’s a hill behind the site, that’s the one that’s moving, not the site itself. We just want to make sure we protect ourselves from that geological condition once we make a decision on putting up the plant,” he said.
Once the solution is approved by the board, construction can be started on stabilizing the slope.
Source: manilastandard.net