Subic power plant faces further delay

Tags:

Posted 5 years ago

Photo Credit: elp.com

Redondo Peninsula Energy Inc. may put on hold the development of a 660-megawatt coal-fired power until 2020 due to construction issues, an official said over the weekend.

RP Energy is a joint venture among Meralco PowerGen Corp., Therma Power Inc. of the Aboitiz Group and Taiwan Cogeneration International Corp.

“The management of RP Energy have engaged a consultant and the consultant’s recommendation is to stabilize the slope first. Issues like this with geological conditions is very tricky. In fact, one of the recommendations I believe, is to let it rest for one rainy season and that’s rainy season up to 2020,” said Aboitiz Power chief operating officer Manny Rubio said.

“There’s a hill behind the site, that’s the one that’s moving, not the site itself. We just want to make sure we protect ourselves from that geological condition once we make a decision on putting up the plant,” he said.

Once the solution is approved by the board, construction can be started on stabilizing the slope.

Source: manilastandard.net

ZubakeryZubakery

Loading Comment

Subic power plant faces further delay

Tags:

Posted 5 years ago

Subic remains top tourist magnet in Region 3

Tags:

Posted 5 years ago

BOC-Port Of Subic Seizes P60M worth of sugar, firecrackers

Posted 5 years ago

Chinese clam poachers making ‘thousands of dollars’ while destroying entire reef

Posted 5 years ago

NLEX spending P1.6b to expand toll road in Subic

Posted 5 years ago

Southeast Asia became dumping ground for plastic waste

Posted 5 years ago

 
Share